25-ID Construction Schedule

  • Project Manager: Robert Winarski/PSC
  • APS Point-of-Contact: Andy Stevens/FAC 
  • Contractor: Enterprise Caratelli and sub-contractor Stevenson Crane
Date     Construction Activity     Expected Vibration Level    
(low, moderate, high)
March 18 Transport of 25-ID panels to the experimental hall floor Low
March 19 Transport of 25-ID panels to the experimental hall floor Low
March 22 Cutting door trenches Moderate
March 23
 Installation of 25-ID roof and wall panels, anchor-drilling
Low
March 24
Installation of 25-ID roof and wall panels, anchor-drilling
Low
March 25
Installation of 25-ID roof and wall panels, anchor-drilling
Low
March 26
Installation of 25-ID roof and wall panels, anchor-drilling
Low