- Project Manager: Robert Winarski/PSC
- APS Point-of-Contact: Andy Stevens/FAC
- Contractor: Enterprise Caratelli and sub-contractor Stevenson Crane
Construction of the 28-ID A to B transport is scheduled to start September 29, 2020. Floor drilling and wedge anchor installation has already been completed. If further drilling is needed, it will be done on a machine studies day.
Date |
Construction Activity |
Expected Vibration Level
(low, moderate, high) |
September 29 |
Transport of stands and coffins to S28 |
Low |
September 30 |
Transport of stands and coffins to S28 |
Low |
October 1 |
Installation of transport stands and body |
Low |
October 2 |
Installation of transport stands and body |
|
Low |
October 5 |
Installation of transport stands and body |
|
Low |
October 6 |
Installation of transport stands and body |
|
Low |
October 7 |
Installation of transport stands and body |
|
Low |
October 8 |
Installation of transport stands and body |
|
Low |
October 9 |
Installation of transport stands and body |
|
Low |
|
|
|
|